LIVE BUILD COSTS

Aug 28
1 min read

What our custom home has cost so far.



TOTAL SPENT THROUGH PHASE 4


$303,397.21



PHASE 0 — PLANS, PERMITS + PRE-BUILD


Phase Total: $88,102.50

Architect + Engineering — $18,618

Truss Design Permit — $3,829.50

GEO / Geotechnical — $2,500

Septic Engineering — $2,500

Well — $16,780

Private Provider — $10,000

Permits + Impact Fees — $33,875


PHASE 1 — SITE PREP + GRADING


Phase Total: $22,500

Site Prep — $3,000

65 Loads of Fill Dirt — $15,000

House Pad — $4,500


PHASE 2 — FOUNDATION


Phase Total: $46,100

Footer Prep — $4,500

Rebar — $2,400

Footer Concrete — $8,000

Stem Wall Block + Fill — $10,000

Foundation Fill — $1,200

Slab — $20,000


PHASE 3 — CONCRETE BLOCK


Phase Total: $58,215

Block Materials + Headers — $25,000

Block Labor — $15,000

Second-Floor Machine / Equipment — $2,215

Concrete Cell Pour — $16,000


PHASE 4 — TRUSSES, WINDOWS + DOORS


Phase Total: $88,479.71

Truss Package Balance — $14,479.71

Windows + 3 Exterior Doors + Slider + Installation — $60,000

Custom 10' × 6' Iron Front Door + Installation — $14,000


TOTAL SPENT THROUGH PHASE 4

$303,397.21